Skip to Content

Category Archives: Projects

tst test

Underground Storage Tank Installation

GCE was chosen to perform installation of two; one 4,000-gallon gasoline and one 4,000-gallon diesel double wall fiber glass underground storage tanks (USTs) with associated piping, containment and a new fuel pump island, pumps, and a new fire suppression system as designed for a public works garage in Malverne, New York according to all applicable regulations.

Project: Underground Tank Installation

Location: Malverne, New York

0 2 Continue Reading →
tst test

Tank Closure and Aboveground Storage Tank Installation

GCE was chosen to perform closure (abandonment in place) of the existing one 3,000-gallon gasoline tank, removal of associated piping along with investigate/verify the conditions of soil/ groundwater and installation of two; one 3,000-gallon gasoline, one 3,000-gallon diesel aboveground storage tanks, associated piping and dispensing system as designed for a police precinct in Yonkers, New York according to all applicable regulations.

Project: Tank Closure and Aboveground Tank Installation

Location: Yonkers, New York

0 1 Continue Reading →
tst test

Tank Removal

GCE was chosen to perform to closure (removal from its place) of the three; one (1) 8,000-gallon, (1) 6,000-gallon and (1) 5,000-gallon gasoline underground storage tanks and associated ancillary equipment by using remove and disposal method and investigate/verify the conditions of soil and groundwater as per Nassau County Petroleum Bulk Storage Regulations Article 15, Section 15-2.6(c) and New York State Department of Environmental Conservation (NYSDEC) regulations for a auto dealer ship in East Meadow, New York.

Project: Tank Removal

Location: East Meadow, New York

0 1 Continue Reading →
tst test

Tank Upgrading

GCE was chosen to perform to upgrade two; one 6,000-gallon gasoline and one 6,000-gallon diesel underground storage tanks, associated  piping, dispensers, tank monitoring system (TMS), new fuel management system (FMS) and replace tank sump systems, and current supply lines along with remedial services for a bus garage in Jericho, New York in accordance with regulatory agencies requirements and based on system tank test passed results.

Project: Tank Upgrading

Location: Jericho, New York

0 1 Continue Reading →
tst test

Built On-site Tank

GCE was chosen to perform remove 5,000-gallon #4 fuel oil underground storage tank and install 1,000-gallon #2 fuel oil single wall steel aboveground storage tank with all associated piping  as designed for a private client according to all applicable regulations.

Project: Built On-site Tank

Location: New York, New York

0 1 Continue Reading →
tst test

Spill Remediation and Site Closure

GCE was chosen to complete removal of the two (2) 8,000-gallon capacity #6 fuel oil steel underground storage tanks (USTs) and associated ancillary equipment by using remove/disposal method and investigate/verify the conditions of soil and groundwater and necessary remedial action to address impacts associated with the release identified during tank removal activity.

The two (2) 8,000-gallon underground storage tanks were closed in accordance the requirements of the New York State Department of Environmental Conservation (NYSDEC), Westchester County Department of Health (WCDH), as well as City of New Rochelle Fire and Police agencies.  During the tank removal activity remedial  work and subsurface investigations were performed at the subject property.   All petroleum impacted soil within the tanks` location was excavated, stockpiled, placed into 20-yards dump trucks and removed from the site and disposed of. In total approximately 7,000-gallons of impacted water and approximately 885-tons of contaminated soil was removed from the Site and disposed of and closure report was completed.

Project: Tank Closure & Spill Remediation and Site Closure

Location: New Rochelle, New York

0 3 Continue Reading →
tst test

Phase I Environmental Site Assessment

GCE was chosen to complete a Phase I Environmental Site Assessment (ESA) on behalf of a confidential Long Island automobile dealership to determine if a property, in its entirety, is subject to recognized environmental conditions* which is often an influential step in the decision-making process for real estate transactions and for general environmental due diligence purposes.  Based on the Phase I findings as a follow up a Phase II Site Investigation was performed and based on findings in situ chemical oxidation a remediation technique used for soil and/or groundwater remediation to reduce the concentrations of Tetrachloroethene (PERC) contaminants.

Project: Phase I Environmental Site Assessment

Location: West Islip, New York

0 1 Continue Reading →
tst test

Phase II Environmental Site Assessment

GCE was chosen to complete a Phase II Environmental Site Assessment (ESA) on behalf of a confidential Long Island developer to determine through subsurface soil sampling and substructure investigation, if potential contamination associated with the areas of environmental concern identified in the previous Phase I Environmental Site Assessment has environmentally impacted the Site. Based on the findings, vertical and horizontal delineation of subsurface contamination-Arsenic impacted soil and vertical delineation of subsurface drainage structure were determined and removed from the Site. The environmental conditions at the property have been evaluated to the applicable regulatory agency and found in compliance with the department’s requirements.

Project: Phase II Environmental Site Assessment

Location: East Hills, New York

0 1 Continue Reading →
tst test

Remedial Investigations/Actions – Site Redevelopment

GCE was chosen to complete a strategic environmental and integrated land development services for the redevelopment of the 16.81-acre private complex within evaluating and implementing the environmental investigation activities, remedial action plan, and remedial action work.  Based on the remediation investigation findings, all contaminated soil was removed and disposed of according to the regulatory agencies (NCDH and NYS DEC).  In total approximately 52,800 gallons of impacted water and approximately 190.28 tons of contaminated soil was removed from the Site and disposed of and closure report was completed

Project: Remedial Investigations/Actions – Site Redevelopment

Location: Woodbury, New York

0 1 Continue Reading →
tst test

Tank Compliance Inspections

GCE was chosen by to perform site inspections of various facilities for compliance of the applicable regulatory agencies.

GCE personal visited each site and prepared inspections reports identifying potential spill pathways, recommendations for follow-up investigations, and suggested improvements to each facility’s Spill Prevention, Control Plan.

Project: Tank Compliance Inspections
Location: New York, New York